How to read a control chart, and the Western Electric rules

What control limits mean, how they differ from specification limits, and the four Western Electric rules for spotting special-cause variation.

All articles

By SigmaForge · · 3 min read

A control chart answers a question every manager asks: did something change, or is this just normal variation? Without a chart, people react to every high or low point, and those reactions often make a process worse. With a chart, you react only to signals.

The parts of a control chart

  • Data points plotted in time order, such as individual measurements, subgroup averages or defect counts.
  • A center line, usually the average of the data.
  • An upper and a lower control limit, typically placed three standard deviations above and below the center line.

The standard deviation used for control limits comes from short-term variation, such as the average moving range on an individuals chart or the average subgroup range on an X-bar and R chart. That is deliberate: it lets the chart detect shifts that a long-term standard deviation would absorb.

Control limits are not specification limits

This is the most common confusion. Specification limits come from the customer and describe what is acceptable. Control limits come from the process data and describe what the process normally does. A process can be in control and still produce parts out of specification, if its normal variation is too wide. It can also be out of control while every part is within specification. Never draw specification limits on a chart of subgroup averages, because averages vary less than individual parts.

Common cause and special cause

Common-cause variation is the background noise built into the process: many small sources that are always present. Special-cause variation comes from something specific and unusual, such as a new batch of material, a worn tool, a different operator, or a change in method. The job of the chart is to separate the two. Common-cause variation is reduced by changing the system. Special causes are found and dealt with one at a time.

The Western Electric rules

The Western Electric rules, published in the 1950s in a Western Electric quality handbook, are a widely used set of tests for special causes. They divide the area between the center line and each control limit into three equal zones, one standard deviation wide: Zone C nearest the center line, then Zone B, then Zone A next to the limit.

  1. 01One point beyond either control limit (more than 3σ from the center line).
  2. 02Two out of three consecutive points beyond 2σ, on the same side of the center line.
  3. 03Four out of five consecutive points beyond 1σ, on the same side of the center line.
  4. 04Eight consecutive points on the same side of the center line.

Rule 1 catches large, sudden changes. Rules 2 and 3 catch moderate shifts sooner than Rule 1 would. Rule 4 catches small, sustained shifts in the average. Other rule sets, such as the Nelson rules, add tests for trends and for unusual patterns like points alternating up and down.

The trade-off of adding rules

Each extra rule makes the chart more sensitive to real shifts, and also increases the chance of a false alarm on a stable process. Using all four rules together is common, but some teams start with Rule 1 alone on a new chart and add the others once the process is stable and well understood. Decide in advance which rules you apply, and write them into the control plan.

A routine for reading any chart

  1. 01Check the chart type matches the data: individuals and moving range for single measurements, X-bar and R or S for subgroups, p or np charts for proportions defective, c or u charts for defect counts.
  2. 02Confirm how the limits were calculated, and from which period of data.
  3. 03Look for points outside the limits first, then apply the zone rules.
  4. 04For any signal, ask what changed at that time, and record the answer on the chart.
  5. 05If there are no signals, leave the process alone. Reacting to common-cause noise, sometimes called tampering, adds variation.

When to recalculate the limits

Recalculate limits after a deliberate, verified change to the process, using data from after the change. Do not recalculate simply because points keep breaking the limits. That is the chart doing its job.